Planned road closures
A guide to planned closures due to road works, public processions and special events.
Overview
We publish official notices about road closures in the council area.
These notices explain:
- when the road closures will begin and end
- which roads will be affected
- what diversions will be in place
This page is a list of these closures, with links to the full notices.
The list is ordered by road closure start dates.
Where you can find general information on road works
You can get up-to-date information on all road works in Scotland by visiting Scottish Road Works Online.
You can also get information on works on trunk roads and motorways by visiting the Traffic Scotland site.
Abercromby Drive/Sunnylaw Road, Bridge of Allan, from 3 July 2024
Reason for closure | Roadworks |
---|---|
Town | Bridge of Allan |
Streets affected | Abercromby Drive Sunnylaw Road |
Start date | 3 July 2024 |
End date | 4 June 2025 |
Times | All day |
B8034, Port of Menteith to Arnprior, from 9 September 2024
Reason for closure | Roadworks |
---|---|
Town | Port of Menteith - Arnprior |
Streets affected | B8034 |
Start date | 9 September 2024 |
End date | 3 November 2024 |
Times | 24hrs |
Laurelhill Place, Stirling, from 29 September 2024
Reason for closure | Roadworks |
---|---|
Town | Stirling |
Streets affected | Laurelhill Place |
Start date | 29 September 2024 |
End date | 1 November 2024 |
Times | 8am to 6pm |
Pirnhall Road, Bannockburn, from 3 October 2024
Reason for closure | Roadworks |
---|---|
Town | Bannockburn |
Streets affected | Pirnhall Road |
Start date | 3 October 2024 |
End date | 8 November 2024 |
Times | 24hrs |
Raploch Road, Raploch, from 14 October 2024
Reason for closure | Roadworks |
---|---|
Town | Raploch |
Streets affected | Raploch Road |
Start date | 14 October 2024 |
End date | 3 December 2024 |
Times | 24hrs |
Spittal Street, Stirling, from 14 October 2024
Reason for closure | Roadworks |
---|---|
Town | Stirling |
Streets affected | Spittal Street |
Start date | 14 October 2024 |
End date | 25 October 2024 |
Times | 8am until 5pm |
Burnside Crescent, Plean, from 21 October 2024
Reason for closure | Roadworks |
---|---|
Town | Plean |
Streets affected | Burnside Crescent |
Start date | 21 October 2024 |
End date | 28 October 2024 |
Times | 8am until 6pm |
St Anne's Crescent, Bannockburn, from 21 October 2024
Reason for closure | Roadworks |
---|---|
Town | Bannockburn |
Streets affected | St Anne's Crescent |
Start date | 21 October 2024 |
End date | 26 October 2024 |
Times | 8am until 6pm |
B822, Fintry, from 28 October 2024
Reason for closure | Roadworks |
---|---|
Town | Fintry |
Streets affected | B822 |
Start date | 28 October 2024 |
End date | 3 November 2024 |
Times | 9am until 5pm |
Lernock Road, Balfron, from 28 October 2024
Reason for closure | Roadworks |
---|---|
Town | Balfron |
Streets affected | Lernock Road |
Start date | 28 October 2024 |
End date | 3 November 2024 |
Times | 9am until 6pm |
Dunglass View, Strathblane, from 28 October 2024
Reason for closure | Roadworks |
---|---|
Town | Strathblane |
Streets affected | Dunglass View |
Start date | 28 October 2024 |
End date | 4 November 2024 |
Times | 24hrs |
B822, Fintry, from 29 October 2024
Reason for closure | Roadworks |
---|---|
Town | Fintry |
Streets affected | B822 |
Start date | 29 October 2024 |
End date | 30 October 2024 |
Times | 9:30am until 3:30pm |
B8033, Kinbuck, from 30 October 2024
Reason for closure | Roadworks |
---|---|
Town | Kinbuck |
Streets affected | B8033 |
Start date | 30 October 2024 |
End date | 30 October 2024 |
Times | 10am until 11:30am |
Station Road, Killearn, from 3 November 2024
Reason for closure | Roadworks |
---|---|
Town | Killearn |
Streets affected | Station Road |
Start date | 3 November 2024 |
End date | 3 November 2024 |
Times | 6pm to 9pm |
B8034, Dunblane, from 4 November 2024
Reason for closure | Roadworks |
---|---|
Town | Arnprior - Port of Menteith |
Streets affected | The Haining |
Start date | 4 November 2024 |
End date | 28 February 2024 |
Times | 24hrs |
A821, Aberfoyle, from 4 November 2024
Reason for closure | Roadworks |
---|---|
Town | Aberfoyle |
Streets affected | A821 |
Start date | 4 November 2024 |
End date | 15 November 2024 |
Times | 9am to 4pm |
East Murrayfield, Bannockburn, from 4 November 2024
Reason for closure | Roadworks |
---|---|
Town | Bannockburn |
Streets affected | East Murrayfield |
Start date | 7 November 2024 |
End date | 14 November 2024 |
Times | 8am to 6pm |
Glinns Road, Kippen, from 4 November 2024
Reason for closure | Roadworks |
---|---|
Town | Kippen |
Streets affected | Glinns Road |
Start date | 4 November 2024 |
End date | 10 November 2024 |
Times | 9am to 4pm |
The Haining, Dunblane, from 6 November 2024
Reason for closure | Roadworks |
---|---|
Town | Dunblane |
Streets affected | The Haining |
Start date | 6 November 2024 |
End date | 22 November 2024 |
Times | 24hrs |
Multiple roads, Plean, from 6 November 2024
Reason for closure | Roadworks |
---|---|
Town | Plean |
Streets affected | Burnside Crescent, Cadgers Brae, Carbrook Drive, Stirling Place, Touchhill Crescent |
Start date | 4 November 2024 |
End date | 11 November 2024 |
Times | 8am to 6pm |
Leckie Road, Gargunnock, from 7 November 2024
Reason for closure | Roadworks |
---|---|
Town | Gargunnock |
Streets affected | Leckie Road |
Start date | 7 November 2024 |
End date | 7 November 2024 |
Times | 9am to 5pm |
Spokers Loan, Balfron, on 10 November 2024
Reason for closure | Special Event |
---|---|
Town | Balfron |
Streets affected | Spokers Loan |
Start date | 10 November 2024 |
End date | 10 November 2024 |
Times | 10:50am to 11:10am |
Multiple roads, Stirling city centre, on 10 November 2024
Reason for closure | Public Procession |
---|---|
Town | Stirling |
Streets affected | Mar Place St John Street Spittal Street Corn Exchange Road |
Start date | 10 November 2024 |
End date | 10 November 2024 |
Times | 11:50am to 12:50pm |
Cleuch Road and Easter Cornton Road, Bridge of Allan, from 10 November 2024
Reason for closure | Roadworks |
---|---|
Town | Bridge of Allan |
Streets affected | Cleuch Road Easter Cornton Road |
Start date | 10 November 2024 |
End date | 13 November 2024 |
Times | All day |
C34, Bridge of Allan, from 11 November 2024
Reason for closure | Roadworks |
---|---|
Town | Bridge of Allan |
Streets affected | C34 |
Start date | 11 November 2024 |
End date | 26 January 2025 |
Times | 7:30pm to 6:00am |
B818, Balfron, from 11 November 2024
Reason for closure | Roadworks |
---|---|
Town | Balfron |
Streets affected | B818 |
Start date | 11 November 2024 |
End date | 17 November 2024 |
Times | 9am to 5pm |
Forglen Crescent, Bridge of Allan, on 12 November 2024
Reason for closure | Roadworks |
---|---|
Town | Bridge of Allan |
Streets affected | Forglen Crescent |
Start date | 12 November 2024 |
End date | 12 November 2024 |
Times | 8am to 6pm |
Kellie Wynd, Dunblane, on 12 November 2024
Reason for closure | Roadworks |
---|---|
Town | Dunblane |
Streets affected | Kellie Wynd |
Start date | 12 November 2024 |
End date | 12 November 2024 |
Times | 9:30am to 6pm |
Castle Road and Dumyat Road, Bridge of Allan, from 13 November 2024
Reason for closure | Roadworks |
---|---|
Town | Bridge of Allan |
Streets affected | Castle Road Dumyat Road |
Start date | 13 November 2024 |
End date | 17 November 2024 |
Times | All day |